P1: Nitrous at Balls in '09

Test Stand

Last Update, 10/25/07 by Stephen Daniel

Progress Notes

  • As of 9/28/07 we have installed the anchors and the pad. Nothing has been added to the tower yet, but this will be sufficient testing the Mark IIId PVC Hybrid.
Click to enlargeFull size image
  • On 10/21 we performed a pair of tests with the Mark-IIId PVC Hybrid. We bolted a thrust block (a piece of 2x4) to the top of the tower with U-bolts. The motor was strapped on with nylon straps. This photo shows the stand and the motor, fully prepped.
  • Movies of the test show the stand was immobile throughout the firing.
Click to enlargeFull size image